| Activity | Unit No. | Completion Date | Unit No. | Completion Date |
| The dummy fuel assemblies are loaded into the reactor core of KK1 | 1 |
Apr-2010
| 2 |
-
|
| Putting Turbine on Barring Gear in TB-1 | 1 |
Mar-2010
| 2 |
-
|
| Commissioning of 220 KV GIS System | 1 |
Dec-2008
| 2 |
-
|
| Erection of NSSS Equipment & pipelines (MCP) | 1 |
July-2008
| 2 |
Apr-2009
|
| Construction of Outer Containment (OC) Dome in RB-1 | 1 |
May-2008
| 2 |
Oct-2008
|
| Construction of Inner Containment (IC) Dome in RB-1 | 1 |
Oct-2007
| 2 |
July-2008
|
| Commissioning of Polar Crane | 1 |
Apr-2007
| 2 |
Dec-2007
|
| Construction of Main Control Room and Auxiliary Building (up to 22.8 M) | 1 |
Apr-2006
| 2 |
Sep-2007
|
| Construction of Emergency Power Supply and Control Building | 1 |
Feb-2006
| 2 |
-
|
| Construction of Turbine Building up to 36.5 M Including Crane beam. | 1 |
Aug-2005
| 2 |
Jan-2007
|
| Construction of Primary Containment Wall upto 43.9M | 1 |
May-2005
| 2 |
Nov-2005
|
| Construction upto + 5.4 Slab | 1 |
Sep-2003
| 2 |
Dec-2003
|
| Completion of 0.00m Slab | 1 |
Mar-2003
| 2 |
June-2003
|
| Completion of Foundation Slab | 1 |
July-2002
| 2 |
Sep-2002
|
| First Pour of Concrete | 1 |
Mar-2002
| 2 |
July-2002
|
| Ground Break | 1 |
Sep-2001
| 2 |
Sep-2001
|