Home Plants Under Construction Rajasthan Atomic Power Project
 
 
Location : Rawatbhata via Kota State : Rajasthan
Unit NumberReactor TypeCapacity (MWe)Schedule Date of Commercial OperationExpected Date of Commercial OperationPhysical Progress
7Pressurised Heavy Water Reactor(PHWR)700Jun-2016June-2016-
8Pressurised Heavy Water Reactor(PHWR)700Dec-2016Dec-2016-
 
Major Milestones
ActivityUnit No.Completion
Month
Unit No.Completion
Month
First pour of concrete7 July-2011 8 Sep-2011
Release calandria vault for end shield erection7 Sep-2013 8 -
Complete alignment & welding of end shield calandria and grout7 - 8 -
Install calandria tubes7 - 8 -
Complete coolant channel installation7 - 8 -
Erection of feeders7 - 8 -
PHT Hydro Test7 - 8 -
Hot Conditioning of PHT System7 - 8 -
Achieve criticality7 - 8 -
Synchronisation7 - 8 -
Commence commercial operation7 - 8 -