| Unit Number | Reactor Type | Capacity (MWe) | Schedule Date of Commercial Operation | Expected Date of Commercial Operation | Physical Progress |
| 4 | Pressurised Heavy Water Reactor(PHWR) | 220 | Sep-2007 | Dec-2010 | 98.63 % as on Dec-2010 |
|
|
| |
|
 |
| Major Milestones |
 |
|
| Activity | Unit No. | Completion Date |
| Commercial operation | 4 |
-
|
| Synchronisation | 4 |
Jan-2011
|
| Criticality | 4 |
Nov-2010
|
| Fuel Loading | 4 |
Nov-2010
|
| Hot conditioning | 4 |
Feb-2008
|
| RB Leak test | 4 |
Dec-2007
|
| PHT Hydro Test | 4 |
Oct-2007
|
| Feeder Installation | 4 |
July-2007
|
| Coolant Channel Installation | 4 |
May-2006
|
| Calandria Tube Installation | 4 |
Mar-2006
|
| Grout Endshield | 4 |
Nov-2005
|
| Release Calandria Vault for EndShield Erection | 4 |
Sep-2004
|
| Raft Completion | 4 |
Sep-2002
|
| First Pour of Concrete | 4 |
May-2002
|
| Ground Break | 4 |
Mar-2001
|
|
|
| |
|
|
|