Home Plants Under Construction KAIGA ATOMIC POWER PROJECT
 
 
Location : Kaiga Dist. Uttar Kannada, State Karnataka
Unit NumberReactor TypeCapacity (MWe)Schedule Date of Commercial OperationExpected Date of Commercial OperationPhysical Progress
4Pressurised Heavy Water Reactor(PHWR)220Sep-2007Oct-201097.25 % as on Jul-2010
 
Major Milestones Achieved
ActivityUnit No.Completion Date
Commercial operation4 -
Synchronisation4 -
Criticality4 -
Fuel Loading4 -
Hot conditioning 4 Feb-2008
RB Leak test4 Dec-2007
PHT Hydro Test 4 Oct-2007
Feeder Installation4 July-2007
Coolant Channel Installation4 May-2006
Calandria Tube Installation4 Mar-2006
Grout Endshield4 Nov-2005
Release Calandria Vault for EndShield Erection4 Sep-2004
Raft Completion4 Sep-2002
First Pour of Concrete4 May-2002
Ground Break4 Mar-2001