| Unit Number | Reactor Type | Capacity (MWe) | Schedule Date of Commercial Operation | Expected Date of Commercial Operation | Physical Progress |
| 3 | Pressurised Heavy Water Reactor(PHWR) | 700 | Jun-2015 | June 2015 | - |
| 4 | Pressurised Heavy Water Reactor(PHWR) | 700 | Dec-2015 | Dec 2015 | - |
|
|
| |
|
 |
| Major Milestones |
 |
|
| Activity | Unit No. | Completion Date | Unit No. | Completion Date |
| First pour of concrete | 3 |
Nov-2010
| 4 |
Mar-2011
|
| Release calandria vault for end shield erection | 3 |
-
| 4 |
-
|
| Complete alignment & welding of end shield calandria and grout | 3 |
-
| 4 |
-
|
| Install calandria tubes | 3 |
-
| 4 |
-
|
| Complete coolant channel installation | 3 |
-
| 4 |
-
|
| Erection of feeders | 3 |
-
| 3 |
-
|
| PHT Hydro Test | 3 |
-
| 4 |
-
|
| Hot Conditioning of PHT System | 3 |
-
| 4 |
-
|
| Achieve criticality | 3 |
-
| 4 |
-
|
| Synchronisation | 3 |
-
| 4 |
-
|
| Commence commercial operation | 3 |
-
| 4 |
-
|
|
|
| |
|
|
|