Location : Tarapur, Boisar, Dist. Thane, Maharashtra
Unit Reactor Type Capacity (MWe) Date of Commercial Operation Cumulative Generation Since
Commercial Operation (MUs)
TAPS Unit-1 BWR 160 October 28, 1969 49532
TAPS Unit-2 BWR 160 October 28, 1969 50979
TAPS Unit-3 PHWR 540 August 18, 2006 76564
TAPS Unit-4 PHWR 540 September 12, 2005 73560
Total 1400 - 250635

 

Generation Statistics during the Current Financial Year (FY 2026-27)
Unit Apr - Aug 2026 (FY 2026-27)
Gross Generation(MUs) Capacity Factor(%)
TAPS Unit-1 337 57
TAPS Unit-2 277 83
TAPS Unit-3 1610 81
TAPS Unit-4 1198 60

Note:
1. Figures are rounded off.

 

Abbreviations:
BWR- Boiling Water Reactor
PHWR- Pressurized Heavy Water Reactor