Location : Tarapur, Boisar, Dist. Thane, Maharashtra
Unit Reactor Type Capacity (MWe) Date of Commercial Operation Cumulative Generation Since
Commercial Operation (MUs)
TAPS Unit-1 BWR 160 October 28, 1969 49260
TAPS Unit-2 BWR 160 October 28, 1969 50702
TAPS Unit-3 PHWR 540 August 18, 2006 75266
TAPS Unit-4 PHWR 540 September 12, 2005 72676
Total 1400 - 247904

 

Generation Statistics during the Current Financial Year (FY 2026-27)
Unit Apr 2026 (FY 2026-27)
Gross Generation(MUs) Capacity Factor(%)
TAPS Unit-1 65 56
TAPS Unit-2 0 0
TAPS Unit-3 311 80
TAPS Unit-4 314 81

Note:
1. Figures are rounded off.
2. TAPS Unit-2 is under shutdown in project mode for refurbishment works.

 

Abbreviations:
BWR- Boiling Water Reactor
PHWR- Pressurised Heavy Water Reactor