S.No. |
Activity |
Unit No. |
Completion Month |
Unit No. |
Completion Month |
01 |
First pour of concrete |
3 |
Nov-2010 |
4 |
Mar-2011 |
02 |
Release calandria vault for end shield erection |
3 |
Feb-2013 |
4 |
Aug-2013 |
03 |
Completed alignment & welding of end shield calandria and grout |
3 |
Dec-2014 |
4 |
Mar-2016 |
04 |
Installed calandria tubes |
3 |
Aug-2015 |
4 |
Aug-2017 |
05 |
Completed coolant channel installation |
3 |
Jun-2016 |
4 |
May-2018 |
06 |
Erection of Feeders |
3 |
Aug-2018 |
4 |
Oct-2021 |
07 |
PHT Hydro Test |
3 |
Feb-2019 |
4 |
Apr-2022 |
08 |
PHT Hot Conditioning |
3 |
Aug-2019 |
4 |
- |
09 |
First Criticality |
3 |
Jul-2020 |
4 |
- |
10 |
Synchronisation with the grid for the first time |
3 |
Jan-2021 |
4 |
- |