S.No. |
Activity |
Unit No. |
Completion Month |
Unit No. |
Completion Month |
01 |
Administrative Approval &Financial Sanction from Government of India (GOI) |
3 |
Mar-2013 |
4 |
Mar-2013 |
02 |
Signing of Contract for delivery of equipment with Long Manufacturing Cycle & First Priority Equipment |
3 |
Dec-2014 |
4 |
Dec-2014 |
03 |
Signing of Contract for Development of Working Documentations (WDs) |
3 |
Dec-2015 |
4 |
Dec-2015 |
04 |
Commencement of Main Plant Excavation Works |
3 |
Feb-2016 |
4 |
Feb-2016 |
05 |
Issue of LOI / WO for Main Plant Civil Works Contract |
3 |
Mar-2017 |
4 |
Mar-2017 |
06 |
Receipt of AERB Consent for First Pour of Concrete (FPC) |
3 |
Jun-2017 |
4 |
Jun-2017 |
07 |
First Pour of Concrete (FPC) |
3 |
Jun-2017 |
4 |
Oct-2017 |
08 |
Manufacturing & Supply of Condensers |
3 |
Sep-2017 |
4 |
Jan-2018 |
09 |
Construction of Reactor Building (up to +0.0M) |
3 |
Sep-2018 |
4 |
Work is in progress |
10 |
Construction of Reactor Building (up to +5.4M) |
3 |
Work is in progress |
4 |
- |